After many months of volunteers working to develop plans with the community and the City, the Probasco Fountain restoration and relocation project will begin. A tentative construction schedule has been developed by the City, and some details are below. All work is subject to weather delays and other unforeseen events. The start date is today. The project is expected to take about 14 weeks and be completed in mid November. We will provide further updates on the project status via email announcements and our Facebook page.

The new location will be approximately 7.5’ west and 3’ north of its current location. The fountain’s top level water feature will be restored and activated at this new location.

Date / Event
Aug 7 / Disconnect utilities
Aug 11-20 / Site preparations
Aug 20 / Remove fountain
Aug 20-Sep 5 / Water main construction
Sep 5-12 / Plumbing work
Sep 15-19 / Pour foundation
Sep 22-30 / Refurbished Fountain returns
Oct 1-31 / Electrical & stone/concrete work
Nov 1-11 /  Light fixtures & benches